July 2015 - Construction Progress Presentation

Scott Barnes, construction manager for the Buford-Thompson Company overseeing the bond construction, updated the school board on July 20, 2015, about the high school transformation project. Work continues on the ninth grade addition, fine arts renovation and addition, cafeteria, learning commons (library), campus office, special education classrooms, locker rooms in gymnasiums and field house, and parking areas. Many areas will be complete for the start of school in August, but several areas will continue through August 2016.
GISD Presentation 7-20-2015.pdf, 7.75 MB; (Last Modified on July 21, 2015)